Question
#2----Jagjit Company designs and builds retaining walls for individual customers. On August 1, there were two jobs in process: Job 93 with a beginning balance
#2----Jagjit Company designs and builds retaining walls for individual customers. On August 1, there were two jobs in process: Job 93 with a beginning balance of $8,800, and Job 94 with a beginning balance of $7,220. Jagjit applies overhead at the rate of $6 per direct labor hour. Direct labor wages average $20 per hour. Data on August costs for all jobs are as follows:
Job 93 | Job 94 | Job 95 | Job 96 | |
Direct materials | $920 | $4,530 | $3,380 | $1,350 |
Direct labor cost | 2,000 | 6,400 | 3,000 | 800 |
During August, Jobs 95 and 96 were started. Job 93 was completed on August 17, and the client was billed at cost plus 40%. All other jobs remained in process.
1. Calculate the number of direct labor hours that were worked on each job in August.
Job 93 | DLH |
Job 94 | DLH |
Job 95 | DLH |
Job 96 | DLH |
2. Calculate the overhead applied to each job during the month of August.
Job 93 | |
Job 94 | |
Job 95 | |
Job 96 |
3. Prepare job-order cost sheets for each job as of the end of August. Refer to Amount Descriptions for the exact wording of text items within your job-order cost sheets. All amount cells must have an entry; enter zeros as needed.
Jagjit Company |
Job-Order Cost Sheets |
August 31 |
1 |
| Job 93 | Job 94 | Job 95 | Job 96 |
2 | Beginning balance | ||||
3 | |||||
4 | |||||
5 | |||||
6 |
4. Calculate the balance in Work in Process on August 31.
The work in process balance on August 31 is .
5. What is the price of Job 93?
The price of Job 93 is .
Partway through the year, Jagjit bought a bulldozer to handle larger jobs. The bulldozer cost $37,500 and is needed for larger commercial jobs. Smaller residential jobs can still be done with the smaller bobcat tractor.
6. CONCEPTUAL CONNECTION: Complete the statement below that outlines how the bulldozers cost could be applied to only those jobs that need the larger equipment.
Create a separate for the acquisition and use of the bulldozer. Treat the bulldozers depreciation, fuel, maintenance, etc. as . Divide this by the anticipated annual hours of use to arrive at the .
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started