3 . 2 For a data migration project ( Mega IT project ) at a large company of which you are the project manager, you

3.2 For a data migration project (Mega IT project) at a large company of which you are the project manager, you must control the costs of the project. Phase 1 will take six (6) months to complete, and you are three (3) months into it. The partial structure of Phase 1 is as follows:
(11)
For A and B, which are sub-accounts of the Phase 1 account, you have the following information:
\table[[\table[[Project],[Sub-],[Account]],BCAC,ACWP,BQAC,AQWP,\table[[Percentage],[complete],[(%)]],BCWS],[A,110,00,77,00,250,00,21,00,51%,54,00],[B,117,00,67,00,321,00,112,00,39%,43,00]]
Calculate the following values, rounding to two (2) decimals:
a. Cost variance (CV)(2)
A: ,CV=?
B: ,CV=?
b. Schedule variance (SV)(2)
A: ,SV=?
B: ,SV=?
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Processes and Supply Chains

Authors: Lee J. Krajewski, Larry P. Ritzman, Manoj K. Malhotra

10th edition

978-013280747, 132807394, 9780132951814, 132807475, 132951819, 978-0132807395

More Books

Students also viewed these General Management questions