3 (25 Marks) A small project consisting of ten activities has the following characteristics: Determine the critical path. Activity Preceding Activity Time Estimate weeks Optimistic
3 (25 Marks) A small project consisting of ten activities has the following characteristics: Determine the critical path. Activity Preceding Activity Time Estimate weeks Optimistic Most likely Pessimestic ABCDEFGH 4 5 12 1.5 5 A 3 4 A 3 4 A 2 4 C . D B.E H 2222 1.5 2 1.5 3 2.5 3.5 1.5 2 2722 2.5 4.5 7.5 2.5 F,G,I 1 2 3