3 ) A company decides to plan a project, with activities, precedence relations and random duration statistics given in the following table: Activity Immediate Predecessors

3) A company decides to plan a project, with activities, precedence relations and random duration statistics given in the following table:
Activity Immediate Predecessors Duration Minimum (weeks) Duration Mode (weeks) Duration Maximum (weeks)
A none 259
B A 168
C A 3512
D B 2412
E B, C 468
F B 678
G D, E 126
H F, G 4616
Answer the following questions:
3.1) What method should be used? Compute the mean and variances for each activity and add them to the table above.
3.2) Draw the project network and label the arcs with the activity name.
3.3) Assuming that the critical path is A-B-P1-E-G-H, compute the probability that this path duration is between 28 weeks and 32 weeks.
3.4) Assuming that the critical path is A-B-P1-E-G-H, compute the number of weeks within which the project will be completed with probability 0.95.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Information Technology Project Management

Authors: Kathy Schwalbe

6th Edition

978-111122175, 1133172393, 9780324786927, 1111221758, 9781133172390, 324786921, 978-1133153726

More Books

Students also viewed these General Management questions

Question

Wk 3 - Apply: Summative Assessment: Using Equity for Financing Exam

Answered: 1 week ago