3 ) A company decides to plan a project, with activities, precedence relations and random duration statistics given in the following table: Activity Immediate Predecessors
A company decides to plan a project, with activities, precedence relations and random duration statistics given in the following table:
Activity Immediate Predecessors Duration Minimum weeks Duration Mode weeks Duration Maximum weeks
A none
B A
C A
D B
E B C
F B
G D E
H F G
Answer the following questions:
What method should be used? Compute the mean and variances for each activity and add them to the table above.
Draw the project network and label the arcs with the activity name.
Assuming that the critical path is ABPEGH compute the probability that this path duration is between weeks and weeks.
Assuming that the critical path is ABPEGH compute the number of weeks within which the project will be completed with probability
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started