Question

1 Approved Answer

3. a) List four (4) general software project risks and describe the risk reduction technique that can be applied to each of the risks you

3. a) List four (4) general software project risks and describe the risk reduction technique that can be applied to each of the risks you have identified. (20 pts.)

b) Risk exposure provides a measure of relative risks;

i) Complete the table by calculating the risk exposure for each of the hazards in the accompanying table. The scores for likelihood and impact are out of 10. (15 pts.)

Hazard

Likelihood

Impact

Risk Exposure

A

2

9

B

8

2

C

10

2

D

3

9

E

4

7

4. a) The project control life cycle is the framework for controlling a project to ensure it meets the project plan. Draw and lable a project control lifecycle diagram (8 pts.)

b) i) A project manager is often required to create a highlight report. Outline four (4) types of information you would expect to be included in a highlight report. (8 pts.)

ii) Name any other two (2) report types that a project manager might be responsible for producing. State who gets them, for what purpose and what they typically contain (12 pts.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Seven NoSQL Databases In A Week Get Up And Running With The Fundamentals And Functionalities Of Seven Of The Most Popular NoSQL Databases

Authors: Aaron Ploetz ,Devram Kandhare ,Sudarshan Kadambi ,Xun Wu

1st Edition

1787288862, 978-1787288867

More Books

Students also viewed these Databases questions