3. A work task has a current cost of 6,000, with a budget cost at this same point of $4.000. The total budget or
3. A work task has a current cost of 6,000, with a budget cost at this same point of $4.000. The total budget or this task is $9,000. The estimated cost at completion for this task is most nearly?.