3. Consider the following process. All steps (A, B, C, D, and E) are necessary to create each finished unit. Each step employs a single

3. Consider the following process. All steps (A, B, C, D, and E) are necessary to create each finished unit. Each step employs a single worker. Task times are shown for each step.

image text in transcribed

What is the hourly utilization of process E (Pack)?

a. 0.5

b. 6

c. 12

d. 0.2

e. 1

10. Consider a five-workstation, worker-paced line, with five manual tasks to be performed before the product is completed, as diagrammed below:

image text in transcribed

The times shown are the times, in minutes, that it takes one worker to perform that task for one unit of product. This line is staffed with six workers, two of whom are assigned to Workstation D. For the next three questions, assume that each of the Tasks A through E are never split among multiple workers. Thus, the two workers doing Task D work on every other unit, each doing all of Task D on the particular unit on which he or she is working. (Assume there is ample equipment so that all workers can perform their tasks). What is the lines capacity in 8 hours day?

a. 96

b. 12

c. 40

d. 51

e. 5

Prepare Front

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials Of Supply Chain Management

Authors: Michael H Hugos

4th Edition

9781119461104

More Books

Students also viewed these General Management questions

Question

Explain what is meant by the click, call, face model.

Answered: 1 week ago