Question
1 Approved Answer
3. Cypress accounting firm has been hired to perform an audit. The audit has been divided into nine activities. The firm has estimated the optimistic
3. Cypress accounting firm has been hired to perform an audit. The audit has been divided into nine activities. The firm has estimated the optimistic (a), pessimistic (b), and most likely (m) times for each task as shown in the table below.
Task Times (weeks) | ||||||
Task | Predecessors | a | m | b | ||
A | None | 4 | 6 | 10 | ||
B | None | 2 | 3 | 5 | ||
C | None | 1 | 2 | 5 | ||
D | A, B | 2 | 3 | 6 | ||
E | A, B, C | 4 | 7 | 12 | ||
F | D, E | 1 | 2 | 4 | ||
G | F | 2 | 4 | 7 | ||
H | F | 3 | 6 | 10 | ||
I | G, H | 1 | 2 | 4 | ||
a. Construct a network diagram for the project.
b. Compute the expected completion time for the project.
c. Compute the probability that the audit will take more than 26 weeks to complete.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started