3. Cypress accounting firm has been hired to perform an audit. The audit has been divided into nine activities. The firm has estimated the optimistic

3. Cypress accounting firm has been hired to perform an audit. The audit has been divided into nine activities. The firm has estimated the optimistic (a), pessimistic (b), and most likely (m) times for each task as shown in the table below.

Task Times (weeks)
Task Predecessors a m b
A None 4 6 10
B None 2 3 5
C None 1 2 5
D A, B 2 3 6
E A, B, C 4 7 12
F D, E 1 2 4
G F 2 4 7
H F 3 6 10
I G, H 1 2 4

a. Construct a network diagram for the project.

b. Compute the expected completion time for the project.

c. Compute the probability that the audit will take more than 26 weeks to complete.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Microeconomics An Intuitive Approach with Calculus

Authors: Thomas Nechyba

1st edition

538453257, 978-0538453257

Students also viewed these Accounting questions

Question

=+b) Find the standard deviations.

Answered: 1 week ago