Question
1 Approved Answer
3.) Domose Inc. planned to use $150 of material per unit but actually used $147 of material per unit, and planned to make1,100 units but
3.) Domose Inc. planned to use $150 of material per unit but actually used $147 of material per unit, and planned to make1,100 units but actually made 900 units. The salesminus-volume variance for materials is A$29,400 unfavorable B $2,700 unfavorable C$30,000 favorable D $2,700 favorable