Question
3. Information is shown below for the last 5 activities in a project with many activities. The network corresponding to this is shown below and
3. Information is shown below for the last 5 activities in a project with many activities. The network corresponding to this is shown below and in the table (M, N, O and P are activities before Q and R). The table also shows the earliest start (ES) times for activities Q and R.
Activity | Length | Predecessor | ES | EF | LS | LF | Slack |
Q | 6 | N,O | 49 | ||||
R | 5 | M,P | 57 | ||||
S | 4 | Q | |||||
U | 9 | R | |||||
V | 8 | S,R |
a) Fill in the table above with the earliest start (ES) and earliest finish (EF) times, the latest start (LS) and latest finish (LF) times and the slack for activities Q, R, S, U and V. (You can also fill in the boxes in the network with ES, EF, LS LF if you wish.)
(2 pt.) b) What is the minimum (earliest) completion time of the project?
c) Which activities are on the critical path?
d) Which activity (or activities) have the greatest slack and how large is that slack?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started