Question

1 Approved Answer

(3). The following is a list of tasks that have to be completed as soon as possible. Activity Predecessors Time (hours) A 5 B

image

(3). The following is a list of tasks that have to be completed as soon as possible. Activity Predecessors Time (hours) A 5 B B,C A,B F C G D,F 5965926 10 H B 8 (a) What are the critical activities for this project? (b) How soon can the project be completed? (c) What is the total float of activity F? (d) If activity D is made shorter by 1 hour, would the project take less time to complete? Explain briefly (e) If activity E is made shorter by 1 hour, would the project take less time to complete? Explain briefly

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Creating Value Along the Supply Chain

Authors: Roberta S. Russell, Bernard W. Taylor

7th Edition

9781118139523, 0470525908, 1118139526, 978-0470525906

More Books

Students also viewed these Mathematics questions

Question

Give examples of lean services.

Answered: 1 week ago