34-The project represented in the diagram below is supposed to start on 1 8 June 2020 . What is the Early Finish Time (EFT) (in

34-The project represented in the diagram below is supposed to start on 18 June 2020. What is the Early Finish Time (EFT) (in date) of activity C (suppose there are no vacations as the seven days of the week are supposed to be all working days)?

image text in transcribed

a.24/06/2020

b.25/06/2020

c.27/06/2020

d.23/06/2020

36-According to the project represented in the AOA diagram below and the information about this project in the table below. What is the duration of Activity F if the duration of the project critical path is 32 days? (assume all durations in days)

image text in transcribed

a.20

b.19

c.21

d.22

A= 3 D= 2 B= 3 C= 3 E= 4 2 A D H 5 B E 1 3 Activity A B D E F G H 1 Duration 5 4 8 4 6 ?? 3 3 4

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Finance for Non Financial Managers

Authors: Pierre Bergeron

7th edition

176530835, 978-0176530839

More Books

Students also viewed these Finance questions