4 . A project has the following activities: Normal Normal Crash Crash Immediate Time Cost Time Cost Activity Predecessors ( weeks ) ( $ )

4. A project has the following activities:
Normal Normal Crash Crash
Immediate Time Cost Time Cost
Activity Predecessors (weeks)($)(weeks)($)
A none 43,00035,000
B A 95,00078,000
C A 47,00047,000
D B, C 66,00048,000
E C 84,00068,000
F D 34,00029,000
G E, F 42,00027,000
a) Draw the network diagram based on normal time.
b) What are potential paths (connected paths) and corresponding durations?
c) What is the expected project completion time based on normal time?
d) What is the most economical way and how much will it cost to reduce the completion time of the project by three weeks?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these General Management questions