Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

4. A Salalah Coffee Company in Salalah, Oman has contracted XYZ M&I Company for the refurbishment and improvement of coffee filling and packing line with

image text in transcribed
image text in transcribed
image text in transcribed
4. A Salalah Coffee Company in Salalah, Oman has contracted XYZ M\&I Company for the refurbishment and improvement of coffee filling and packing line with twenty-five Filling and Packaging machines. Table 4-1 shows the activities for the maintenance and improvement project prepared by XYZ M\&I Company. The Salalah Coffee Company will penalize 2500 OMR for every day of delay of the project implementation. The project can be crashed using the optimistic time estimates as shown in Table 4-1. Different resources are shown in the Table 4-2. Perform the following: (i) Using a Microsoft Project develop a Gantt chart and Network diagram for M\&I project contracted and determine the critical path. How long is the project expected to take? [10] (ii) What is the probability of finishing the M\&I project 1 week ahead of the expected completion date? [8] (iii) If it is necessary to crash to 2 weeks earlier, how would XYZM&I Company do so, and at what costs? As noted in the case, assume that optimistic time estimates can be used as crash time. [10] (iv) Assign the different resources in the Gantt chart and generate dashboard and cash flow report in the MS Project. [7] [Total marks 35] Title 4-1: Coffee Packing Line Maintenance \& Improvement Project Title 4-2: Manpower Resource Details for Coffee Packing Line M\&l Project 4. A Salalah Coffee Company in Salalah, Oman has contracted XYZ M\&I Company for the refurbishment and improvement of coffee filling and packing line with twenty-five Filling and Packaging machines. Table 4-1 shows the activities for the maintenance and improvement project prepared by XYZ M\&I Company. The Salalah Coffee Company will penalize 2500 OMR for every day of delay of the project implementation. The project can be crashed using the optimistic time estimates as shown in Table 4-1. Different resources are shown in the Table 4-2. Perform the following: (i) Using a Microsoft Project develop a Gantt chart and Network diagram for M\&I project contracted and determine the critical path. How long is the project expected to take? [10] (ii) What is the probability of finishing the M\&I project 1 week ahead of the expected completion date? [8] (iii) If it is necessary to crash to 2 weeks earlier, how would XYZM&I Company do so, and at what costs? As noted in the case, assume that optimistic time estimates can be used as crash time. [10] (iv) Assign the different resources in the Gantt chart and generate dashboard and cash flow report in the MS Project. [7] [Total marks 35] Title 4-1: Coffee Packing Line Maintenance \& Improvement Project Title 4-2: Manpower Resource Details for Coffee Packing Line M\&l Project

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Understanding Financial Statements A Manager S Guide

Authors: David S. Murphy Ph.D. ,Ernest W. Murphy

1st Edition

1530688787, 978-1530688784

More Books

Students also viewed these Accounting questions

Question

1. Discuss the four components of language.

Answered: 1 week ago

Question

a. How many different groups were represented?

Answered: 1 week ago