4. Calculate the amount of revenue and gross profit to be recognized in each of the three years, assuming the following costs incurred and costs to complete information: 5. Calculate the amount of revenue and gross profit to be recognized in each of the three years, assuming the following costs incurred and costs to complete information: P 6-10 Long-term contract; revenue recognition over time LO6-8, LO6-9 In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Westgate recognizes revenue over time according to percentage of completion. Required: 1. Calculate the amount of revenue and gross profit to be recognized in each of the three years. 2. Prepare all necessary journal entries for each of the years (credit "Cash, Materials, etc," for construction costs incurred). 3. Prepare a partial balance sheet for 2024 and 2025 showing any items related to the contract. Indicate whether any of the amounts shown are contract assets or contract liabilities. 4. Calculate the amount of revenue and gross profit to be recognized in each of the three years, assuming the following costs incurred and costs to complete information: P 6-10 Long-term contract; revenue recognition over time LO6-8, LO6-9 In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Westgate recognizes revenue over time according to percentage of completion. Required: 1. Calculate the amount of revenue and gross profit to be recognized in each of the three years. 2. Prepare all necessary journal entries for each of the years (credit "Cash, Materials, etc," for construction costs incurred). 3. Prepare a partial balance sheet for 2024 and 2025 showing any items related to the contract. Indicate whether any of the amounts shown are contract assets or contract liabilities. 4. Calculate the amount of revenue and gross profit to be recognized in each of the three years, assuming the following costs incurred and costs to complete information: P 6-11 Long-term contract; revenue recognition upon completion LO6-9 [This is a variation of P6 - 10 modified to focus on revenue recognition upon project completion.] Required: Complete the requirements of P 6-10, assuming that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time. 4. Calculate the amount of revenue and gross profit to be recognized in each of the three years, assuming the following costs incurred and costs to complete information: 5. Calculate the amount of revenue and gross profit to be recognized in each of the three years, assuming the following costs incurred and costs to complete information