Question
1 Approved Answer
4. Data for labor used in the production of sneakers Standard: .25 hours per sneaker at $11.00 per hour Actual quantity produced: 25,000 sneakers Quantity
4. Data for labor used in the production of sneakers Standard: .25 hours per sneaker at $11.00 per hour Actual quantity produced: 25,000 sneakers Quantity used: 6,000 hours, total cost $69,000 What is the labor efficiency variance? A. $2,750 Favorable B. $2,750 Unfavorable
Step by Step Solution
There are 3 Steps involved in it
Step: 1