4 . Economy Power requires an upgrade of a complex piece of equipment in their network. There are nine activities required to complete the upgrade.

4. Economy Power requires an upgrade of a complex piece of equipment in their network. There are
nine activities required to complete the upgrade. The table below summarizes the relationship of each
activity and their duration. It also included the costs of each activity and crash costs if needed. (20
points)
Activity Immediate
Predecessors
Normal
Duration
(hours)
Crash
Time
(hours)
Normal
Cost
Crash cost
A None 53300500
B A 21350500
C A 1212600600
D None 32125725
E B 55225225
F D 11275875
G B 74200800
H E,C 215001000
I G.F 108125725
J H,I 66365365
a. Draw the AON network (2 points)
b. Label the network completing the nodes for ES,EF,LS,LF (5 points)
c. Label the slack time (1 point)
d. Identify the critical path (1 point)
e. What is the earliest finish time? (1 point

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managing Supply Chain And Operations An Integrative Approach

Authors: S. Thomas Foster, Scott E. Sampson, Cynthia Wallin, Scott W. Webb

2nd Edition

978-0134739830, 0134739833

More Books

Students also viewed these General Management questions

Question

How can the use of debt serve to discipline managers?

Answered: 1 week ago