Question
1 Approved Answer
4. Given the following Mast production schedule, a) compute the available-to-promise quantities. Model B BI Week 0 1 2 3 4 5 6 7
4. Given the following Mast production schedule, a) compute the available-to-promise quantities. Model B BI Week 0 1 2 3 4 5 6 7 8 MPS 20 0 20 20 10 20 20 Committed orders 10 10 0 10 30 0 10 20 Inventory ATP: Cummulative ATP:D 0 b) (added) If a new customer called to place an order of 10 units in week 4, can you accept the order without changing your MPS? c) (added) Given you committed the new order made in b), another customer place an order of 20 units in week 5, can you accept the order without changing your MPS?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started