4 . Typically in construction contracts there will be a provision awarding damages to the buyer at X amount of dollars per day

4. Typically in construction contracts there will be a provision awarding damages to the buyer at "X" amount of dollars per day for each day the builder is late in completing the work. The parties to the contract agree upon this amount in advance because they know the buyer will incur added costs, or will lose profits, because of the delay. What type of damages are these contractually fixed payments?
a. Nominal
b. Liquidated
c. Punitive
d. Compensatory
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Power Of Laws

Authors: Terence K Moloisane

1st Edition

B08Z7HTFTJ, B0CP2YDQDK

More Books

Students also viewed these General Management questions