Question

1 Approved Answer

4. Using the table below, answer the five questions. (40 pts.) Please note that you must provide correct answers AND reasoning to earn points. Activity

4. Using the table below, answer the five questions. (40 pts.) Please note that you must provide correct answers AND reasoning to earn points.

Activity a m b Predecessors
A 8 10 13 -
B 6 7 9 A
C 3 4 6 A
D 12 18 24 C
E 5 7 10 B
F 7 10 12 E
G 5 7 11 D, F
H 13 16 20 F
I 10 14 17 G, H

(a=optimistic; m=most likely; b=pessimistic)

a. Determine the expected times and variances for each activity. Your answer must be a table.

b. Construct a project network diagram. Insert your diagram in your Word file.

c. Using the network diagram, determine the EST, EFT, LST, LFT, slack time for each activity, critical path, and project completion time. You can expand the table you draw for question 4.a. by adding more columns.

d. What is the probability that the project will be finished in 67 days?

e. What is a new expected completion time when the project needs to be done on time with a 95% probability?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Foundations of Operations Management

Authors: Larry P. Ritzman, Lee J. Krajewski, Manoj K. Malhotra, Robert D. Klassen

3rd Canadian Edition

132317532, 978-0133076783, 133076784, 978-0132317535

More Books

Students also viewed these General Management questions

Question

Perform the multiplication. 1. 2. 3. 4. 5. 3. 4] 2][3 5] -1][3] [2

Answered: 1 week ago