Question
42.On a scrum project Loretta is the product owner and Kunika is the Scum Master. The current sprint is halfway through. The team receives a
42.On a scrum project Loretta is the product owner and Kunika is the Scum Master. The current sprint is halfway through. The team receives a duly approved change request. Loreta and Kunika are convinced that it is an urgently needed change.
a. Loretta and Kunika can cancel the sprint only jointly and restart it to accommodate the change request.
b. Kunika can cancel the sprint and restart it to accommodate the change request
c. The current sprint can not be cancelled. The team has to wait for the next sprint to include the change request.
d. Loretta can cancel the sprint and restart it to accommodate the change request.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started