43. Which one is correct in project scheduling? A) Lead means overlap. B) Overlap means the same as lag. C) Lead means the same as

image text in transcribed
image text in transcribed
image text in transcribed
image text in transcribed
43. Which one is correct in project scheduling? A) Lead means overlap. B) Overlap means the same as lag. C) Lead means the same as lag. D) Each lead, overlap, and lag means something different. 28. Which of the following terms is used to describe a risk event that has a high impact and a high frequency? A) Severe. B) Critical. C) Serious. D) Controlled. 25. Which of the following is considered a threat transfer risk response strategy in a construction project? A) Training labourers with the latest machinery technology B) Purchasing an insurance policy for the project C) Installing security cameras at the construction site D) Avoiding hiring unprofessional labour 3. Which one is not a characteristic of a process compared to a project? A) Well-established systems B) Support the status quo C) One shot limited life D) Greater certainty 4. What is not the responsibility of a Web design project manager? A) managing resources B) Selecting a team C) Cost estimating and budgeting D) Design Website logo and template

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_step_2

Step: 3

blur-text-image_step3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these Finance questions