47 of 75 Your project is behind schedule and your project board has instructed you to make up for lost time. What is your
47 of 75 Your project is behind schedule and your project board has instructed you to make up for lost time. What is your best course of action? Change the critical path. Identify critical path activities that can be conducted in parallel earlier. Request that the project board provide more time to complete the project. Add more resources and/or fast track any of the activities which are not on the critical path. ct D