Question

1 Approved Answer

4.Jana Crebs is a contractor for the construction of three large office buildings. At the beginning of 2010, two (2) buildings were in progress. The

4.Jana Crebs is a contractor for the construction of three large office buildings. At the beginning of 2010, two (2) buildings were in progress. The following data describe the status of these buildings at the beginning of the year:

ContractPrice

Costs Incurred to Jan. 1, 2010

Est'd. Costs to Complete

as of 1/1/2010

Building 1

P 4,000,000

P2,070,000

P1,380,000

Building 2

9,000,000

6,318,000

1,782,000

During 2010, the following costs were incurred

Building 1 P930,000 (estimated cost to complete of 12/31/2010, P750,00)

Building 2 P1,800,000 (job completed)

Compute the recognized revenue in 2010, assuming:

Percentage-of-Cost

Completion MethodRecovery Method

A.

P2,780,000

P3,612,000

B.

P2,780,000

2,682,000

C.

50,000

882,000

D.

50,000

180,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting Tools For Business Decision Making

Authors: Jerry J Weygandt, Paul D Kimmel, Jill E Mitchell

9th Edition

1119754054, 9781119754053

More Books

Students also viewed these Accounting questions

Question

6. What information processes operate in communication situations?

Answered: 1 week ago

Question

3. How can we use information and communication to generate trust?

Answered: 1 week ago