Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

5. [30 points] Consider a project with following precedence relationships and activity times. Activity Immediate Optimistic Most Likely Pessimistic Time Predecessor Time Time A --

image text in transcribed
5. [30 points] Consider a project with following precedence relationships and activity times. Activity Immediate Optimistic Most Likely Pessimistic Time Predecessor Time Time A -- 2 2.5 6 B -- 10 11 12 C A 5 6.5 11 D B, C 11 13 15 B 8 9.5 14 71 D 4.5 5.5 9.5 G E 3.5 5 5.5 H F. G 6.5 7.5 11.5 a. Calculate the expected activity duration (t ), variance for each activity, ES, EF, LS, and LF times and the slack for each activity. Show the values in a table (activity schedule). What is the critical path for the project? Show all work to earn credit. b. What is the probability of completing the project in 35 weeks? Show all work to earn credit. C. If the activity B can be finished in 10 weeks, D in 11 weeks, and E in 8 weeks, recalculate the expected project completion time. Show all work. d. Using MS Project (or any other software), create a Gantt chart for the project based on ES and EF times

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management Awareness And Change

Authors: Frank Martin , John Thompson , Jonathan M.Scott

8th Edition

1473726336, 978-1473726338

More Books

Students also viewed these General Management questions

Question

=+ b. A change in weather patterns increases the depreciation rate.

Answered: 1 week ago