5. A project involving the installation of a computer system consists of eight activities as shown in the activity table below: Activity Immediate Predecessor Time

5.

A project involving the installation of a computer system consists of eight activities as shown in the activity table below:

Activity Immediate Predecessor Time (weeks)

A Equipment acquisition & Preparation -- 3

B Data conversion &Testing -- 6

C User Training A 2

D Parallel Run B, C 5

E Troubleshooting & Observation D 4

F Fine-tuning E 3

G Advanced User Training B, C 9

H Signoff F, G 3

5.1. Draw the PERT network for this project. [14]

5.2. Identify the critical path. [02]

5.3. What is the expected completion time for the project? [02]

5.4. Identify three activities that can be delayed and for each, determine the slack. [03]

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Securing SQL Server Protecting Your Database From Attackers

Authors: Denny Cherry

2nd Edition

1597499471, 978-1597499477

Students also viewed these Databases questions