5. A project is expected to generate earnings before taxes (EBT) of $75,000 per year. Annual depreciation from the project is $45,000 and the firms
5. A project is expected to generate earnings before taxes (EBT) of $75,000 per year. Annual depreciation from the project is $45,000 and the firms tax rate is 40%. Determine the projects annual net cash flows.