5 A project is planned for twelve months at the total cost of $120,000, which will be spent equally over the periods. It is now
5 A project is planned for twelve months at the total cost of $120,000, which will be spent equally over the periods. It is now month 4 and your project's CPI is .9091 and its SV is $10,000. How is the project performing