5. Below is the activity table for a Build A House project: Draw Gantt, Network diagram and identify critical path for the chart below: S.No
5. Below is the activity table for a "Build A House" project: Draw Gantt, Network diagram and identify critical path for the chart below:
S.No | Activity | Duration (in weeks) | Predecessor |
A. | Foundation | 2 | N/a |
B. | Walls | 1 | A |
C. | Roof | 2 | B |
D. | Windows, Doors | 1 | B,C |
E. | Plumbing | 1 | D |
F. | Electric | 2 | D |
G. | Painting | 1 | E,F |
H. | Flooring | 2 | G |