Question

1 Approved Answer

5. Below is the activity table for a Build A House project: Draw Gantt, Network diagram and identify critical path for the chart below: S.No

5. Below is the activity table for a "Build A House" project: Draw Gantt, Network diagram and identify critical path for the chart below:

S.No

Activity

Duration (in weeks)

Predecessor

A.

Foundation

2

N/a

B.

Walls

1

A

C.

Roof

2

B

D.

Windows, Doors

1

B,C

E.

Plumbing

1

D

F.

Electric

2

D

G.

Painting

1

E,F

H.

Flooring

2

G

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Database Systems Design Implementation And Management

Authors: Peter Rob, Carlos Coronel

6th International Edition

061921323X, 978-0619213237

More Books

Students also viewed these Databases questions

Question

Solve 12X 7

Answered: 1 week ago