. 5. FFF Company has accepted a project of constructing a 20-storey condominium in BGC at a fixed price contract of P60,000,000. The project is

image text in transcribed

. 5. FFF Company has accepted a project of constructing a 20-storey condominium in BGC at a fixed price contract of P60,000,000. The project is expected to be completed in three years. The details of the costs incurred in the 1st year are: Cost of labor in the site - P2,500,000 Cost of construction materials, including P500,000 of special materials to be used in Year 2-P12,000,000 Depreciation of construction equipment and other overhead in the site - P2,800,000 Depreciation of idle construction equipment - P900,000 Paid and incurred rectification work - P260,000 Miscellaneous expenses incurred by brokers and sales agents in pre-selling the units - P1,500,000 Total estimated costs at completion - P48,000,000 Determine the following: a. Contract revenue b. Cost of revenue c. Gross profit (loss) to be recognized

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Internal Auditing Assurance And Advisory Services

Authors: Kurt R. Reding, Paul J. Sobel, Urton L. Anderson, Michael J. Head, Sridhar Ramamoorti, Mark Salamasick, Cris Riddle

5th Edition

1634541367, 978-1634541367

More Books

Students also viewed these Accounting questions

Question

What can Chandra do to correct her mistake?

Answered: 1 week ago