Question
5) in 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed
5) in 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:
Cost incurred during the year 2021 2022 2023
$2,581,000 $2,347,000 $3,049,200
Estimated costs to complete 6,319,000 $2,772,000 0
as of year-end
Billings during the year $2,090,000 $2,838,000 $5,072,000
Cash collections during the year 1,845,000 2,900,000 $5,255,000
Westgate recognizes revenue over time according to percentage of completion.
what is the amount of revenue and gross profit(loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information.(Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.)
2021 2022 2023
Costs incurred during the year $2,581,000 $3,845,000 $3,245,000
Estimated costs to finish as of year-end 6,319,000 3,145,000 0
2021 2022 2023
REVENUE
GROSS PROFT OR LOSS
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started