Question
5) The optimistic, most probable, and pessimistic time estimates for the activities of the airline's between-flight operation (in minutes) are as follows: Activity A
5) The optimistic, most probable, and pessimistic time estimates for the activities of the airline's between-flight operation (in minutes) are as follows: Activity A Optimistic (a) Most Probable (m) Pessimistic (b) 1 2 3 4 C 2 5 8 D 7 10 13 E 3 4 5 F 5 7 9. G 7 10 13 8. 6. H. 5 11 I 4 8 J 7 10 13 K 8 9. 10 L 8 10 12 M 9. 11 13 i) Calculate the expected duration, the variance and determine the critical path of the project. (5 marks) ii) What is the probability of the project completed on time if the project is given a 55-minute deadline? (2 marks)
Step by Step Solution
3.25 Rating (154 Votes )
There are 3 Steps involved in it
Step: 1
Expected Duration Te ta4tmtb6 Variance Vt tpta6 2 i Activity Optimi...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
OM operations management
Authors: David Alan Collier, James R. Evans
5th edition
1285451376, 978-1285451374
Students also viewed these Finance questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App