5. When monitoring the success of an improvement project, what graphic tool would be used to evaluate variation in key performance parameters? Pareto chart Control
5. When monitoring the success of an improvement project, what graphic tool would be used to evaluate variation in key performance parameters?
Pareto chart | ||
Control chart | ||
Histogram | ||
Flowchart |