Question
5. Your project to obtain charitable donations is now 30 days into a planned 40-day project. The project is divided into three activities. The first
5. Your project to obtain charitable donations is now 30 days into a planned 40-day project. The project is divided into three activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 25 days of the project and to bring in $25,000. Even though we are 30 days into the project, we still see that we have only 90 percent of this activity complete. The second activity related to company donations and is scheduled to run for 30 days starting on day 5 relates to company donations and extending through day 35. We estimate that, even though we should have 84% (25/30) of this activity complete, it is actually only 50% complete. This part of the project was scheduled to bring in $150,000 in donations. The final activity is for matching funds. This activity is scheduled to run the last 10 days of the project and has not started. It is scheduled to bring in an additional $50,000. So far, $175,000 has actually been brough in on a project. Calaculate the Schedule Variance, Schedule Performance Index, and Cost (actually value in this case) Performance Index. How is the project going?
(Hint: Note that this problem is different since revenue rather than cost is the relevant measure. Use care in how the measures are interpreted.)
PLEASE SHOW PROOF OF CALCULATIONS AND HOW ANSWER WAS OBTAINED.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started