Question

1 Approved Answer

5.1. A work center has the following open and planned orders for week 4. Calculate the total standard time required (load). Order quality Setup time

5.1. A work center has the following open and planned orders for week 4. Calculate the total standard time required (load).

Order quality Setup time (hours)

Run time

(hours/piece)

Total time

(hours)

Release orders 125 200 0.5 0.1
345 70 0.75 0.05
Planned orders 565 80 1.00 0.25
785 35 1.50 0.15
Total time (standard hours)

5.2. Back schedule the following shop order. All times are given in days. Move time between operations is 1 day, and wait time is 1 day. Due date is day 150. Assume orders start at the beginning of a day and fini sh at the end of a day.

Operation number Work center Operation time (days) Queue time (days) Arrival date Finish date
10 111 2 4
20 130 4 5
30 155 1 2
Stores 150

5.3. Over the previous three weeks a work center produced 36, 43, and 35 standard hours of work. What is the measured capacity?

a. 114 standard hours

b. 36 standard hours

c. 38 standard hours

d. 43 standard hours

e. cannot be determined with this data

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials of Management

Authors: Andrew J. DuBrin

9th Edition

538478233, 2900538478235, 978-0538478236

More Books

Students also viewed these General Management questions

Question

LO14.2 Discuss how game theory relates to oligopoly.

Answered: 1 week ago