Question
5.1. A work center has the following open and planned orders for week 4. Calculate the total standard time required (load). Order quality Setup time
5.1. A work center has the following open and planned orders for week 4. Calculate the total standard time required (load).
Order quality | Setup time (hours) | Run time (hours/piece) | Total time (hours) | |
Release orders 125 | 200 | 0.5 | 0.1 | |
345 | 70 | 0.75 | 0.05 | |
Planned orders 565 | 80 | 1.00 | 0.25 | |
785 | 35 | 1.50 | 0.15 | |
Total time (standard hours) |
5.2. Back schedule the following shop order. All times are given in days. Move time between operations is 1 day, and wait time is 1 day. Due date is day 150. Assume orders start at the beginning of a day and fini sh at the end of a day.
Operation number | Work center | Operation time (days) | Queue time (days) | Arrival date | Finish date |
10 | 111 | 2 | 4 | ||
20 | 130 | 4 | 5 | ||
30 | 155 | 1 | 2 | ||
Stores | 150 |
5.3. Over the previous three weeks a work center produced 36, 43, and 35 standard hours of work. What is the measured capacity?
a. 114 standard hours
b. 36 standard hours
c. 38 standard hours
d. 43 standard hours
e. cannot be determined with this data
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started