6. [10] Suppose thre are four jobs in the system: P1, P2, P3, P4. P1, P2, P3, P4 require, 8, 4, 12, 2 unit of
6. [10] Suppose thre are four jobs in the system: P1, P2, P3, P4. P1, P2, P3, P4 require, 8, 4, 12, 2 unit of CPU time respectively and the dispatch latency is 1 unit of CPU time. Draw a Gantt chart to show how the processes would be scheduled using JF) shortest job first, and RR) round robin with time quantum = 2, Find the CPU lization, average response time, average wait time and average turnaround time for each of the method