6. Consider a project consisting of the following activities. Activity Immediate Normal Time | Crash Time Normal Cost Crash Cost Predecessors (weeks) (weeks) $ $

image text in transcribed
6. Consider a project consisting of the following activities. Activity Immediate Normal Time | Crash Time Normal Cost Crash Cost Predecessors (weeks) (weeks) $ $ A None 4 3 3000 6000 B None 4 3 5000 7000 C A 9 7 2000 6000 D A, B 2 2 3000 3000 E B 15 12 4000 7000 F C.D 7 5 4000 5000 G E,F 5 3 2000 5200 a) How would you crash this project by 2 weeks? What is the cost? b) Suppose your client would like the project completed in 23 weeks. The late penalty is $300 per day and overhead costs the firm $500 per day. How would you crash this project

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management

Authors: Stephen P. Robbins, Mary A. Coulter

15th Edition

9780136714491

More Books

Students also viewed these General Management questions

Question

3. If possible, break the presentation into clear steps or stages.

Answered: 1 week ago

Question

Describe the role of HRD practitioners in OD interventions

Answered: 1 week ago