6 points Select the fact(s) below that would go under a heading "Introduction/Background/Current Status" in the Progress Report for the above noted renovation project. The remainder of the materials costs you estimate is $85,000 Original quote you gave your client was $475,000 to complete the entire job As a result, costs overall will not be higher than expected. The resurfacing of all wood floors, replacement of drywall, and installation of lighting systems will take place August 5 to August 18. Work is progressing on schedule The remainder of the labour costs you estimate is $73,000 Costs of materials are coming in higher than you quoted her Labour costs to date are S217.000 Work is being done faster than expected so labour costs will probably end up lower Replacement of heating and air conditioning system is in the preliminary stages You said you would be finished by August 20 The upgrading of the central office and meeting room has been scheduled for completion from July 15 10 August 4 There should be no difficulties in finishing all work by the scheduled completion date Materials costs to date are S90 500 As of July 6, all plumbing work has been done and the o rcuit breaker panels meters service outlets, and all sub-flooring have been installed 6 points Select the fact(s) below that would go under a heading "Introduction/Background/Current Status" in the Progress Report for the above noted renovation project. The remainder of the materials costs you estimate is $85,000 Original quote you gave your client was $475,000 to complete the entire job As a result, costs overall will not be higher than expected. The resurfacing of all wood floors, replacement of drywall, and installation of lighting systems will take place August 5 to August 18. Work is progressing on schedule The remainder of the labour costs you estimate is $73,000 Costs of materials are coming in higher than you quoted her Labour costs to date are S217.000 Work is being done faster than expected so labour costs will probably end up lower Replacement of heating and air conditioning system is in the preliminary stages You said you would be finished by August 20 The upgrading of the central office and meeting room has been scheduled for completion from July 15 10 August 4 There should be no difficulties in finishing all work by the scheduled completion date Materials costs to date are S90 500 As of July 6, all plumbing work has been done and the o rcuit breaker panels meters service outlets, and all sub-flooring have been installed