6. Within-firm risk and beta risk Understanding risks that affect projects and the impact of risk consideration Yatta Net International has manufacturing, distribution, retail, and
6. Within-firm risk and beta risk
Understanding risks that affect projects and the impact of risk consideration
Yatta Net International has manufacturing, distribution, retail, and consulting divisions. Projects undertaken by the manufacturing and distribution divisions tend to be low-risk projects, because these divisions are well established and have predictable demand. The company started its retail and consulting divisions within the last year, and it is unknown if these divisions will be profitable. The company knew that opening these new divisions would be risky, but its management believes the divisions have the potential to be extremely profitable under favorable market conditions. The company is currently using its WACC to evaluate new projects for all divisions.
If Yatta Net International does not risk-adjust its discount rate for specific projects properly, which of the following is likely to occur over time? Check all that apply.
The firm will increase in value.
The firm could potentially reject projects that provide a higher rate of return than the company should require.
The firms overall risk level will increase.
How do managers typically deal with within-firm risk and beta risk when they are evaluating a potential project?
Quantitatively
Subjectively
Consider the case of another company. Turnkey Printing is evaluating two mutually exclusive projects. They both require a $1 million investment today and have expected NPVs of $200,000. Management conducted a full risk analysis of these two projects, and the results are shown below.
Risk Measure | Project A | Project B |
---|---|---|
Standard deviation of projects expected NPVs | $80,000 | $40,000 |
Project beta | 0.9 | 1.1 |
Correlation coefficient of project cash flows (relative to the firms existing projects) | 0.7 | 0.5 |
Which of the following statements about these projects risk is correct? Check all that apply.
Project A has more stand-alone risk than Project B.
Project A has more corporate risk than Project B.
Project A has more market risk than Project B.
Project B has more market risk than Project A.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started