60 (Mandatory) (1 point) A(n) _____ on a project is a significant event that normally has no duration. Question 60 options: a) schedule baseline b)
60 (Mandatory) (1 point) A(n) _____ on a project is a significant event that normally has no duration. Question 60 options: a) schedule baseline b) milestone c) activity attribute d) activity sequence