Question

1 Approved Answer

6-1) An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is

6-1)

An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is 18 minutes. The line will operate for 450 minutes per day.

a.

What are the minimum and maximum cycle times?(Round your answers to 1 decimal place.)

Minimum cycle time minutes
Maximum cycle time minutes

b.

What range of dailyoutput is theoretically possible for the line?(Round your answers to 1 decimal place. Enter the smaller value in the first box and the larger value in the second box.)

Range of output to units/day

c.

What is the minimum number of workstations needed if the maximum output rate is to be sought?(Round up your answer to the next whole number.)

Minimum number of workstations

d.

What cycle time will provide an output rate of 125 units per day?(Round your answer to 1 decimal place.)

Cycle time min/cycle

e.

What output potential will result if the cycle time is (1) 9 minutes? (2) 15 minutes?

Cycle Time Potential Output
(1) units
(2) units

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting For Governmental And Nonprofit Entities

Authors: Jacqueline Reck, Suzanne Lowensohn, Daniel Neely

19th Edition

1260118851, 9781260118858

More Books

Students also viewed these Accounting questions

Question

How flying airoplane?

Answered: 1 week ago