6-3) For the set of tasks given below, do the following: Task Task Time(seconds) Immediate Predecessor A 45 - B 11 A C 9 B
6-3)
For the set of tasks given below, do the following: |
Task | Task Time(seconds) | Immediate Predecessor |
A | 45 | - |
B | 11 | A |
C | 9 | B |
D | 50 | - |
E | 26 | D |
F | 11 | E |
G | 12 | C |
H | 10 | C |
I | 9 | F, G, H |
J | 10 | I |
193 | ||
b. | Determine the minimum and maximum cycle times in seconds for a desired output of 500 units in a seven-hour day.(Round your answers to 1 decimal place.) |
The minimum cycle time | seconds |
The maximum cycle time | seconds |
c. | Determine the minimum number of workstations for output of 500 units per day.(Round up your answer to the next whole number.) |
Minimum number of workstations |
d. | Balance the line using thegreatest positional weightheuristic. Break ties with themost following tasksheuristic. Use a cycle time of 50 seconds. |
Work stations | Following Tasks |
I | (Click to select)ACEBD |
II | (Click to select)CFBDA |
III | (Click to select)CABB, E, CA, E, C |
IV | (Click to select)G, HGCG, F, H, IF, A, G |
V | (Click to select)CBJAD |
e. | Calculate the percentage idle time for the line using the 50 second cycle time.(Round your answer to 1 decimal place. Omit the "%" sign in your response.) |
Percentage of idle time | % |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started