7 4 . Consider the following statements: In the critical path method of construction planning, Free Float can be . 1 . Greater than Total

74. Consider the following statements:
In the critical path method of construction planning, Free Float can be.
1. Greater than Total Float.
2. Greater than Independent Float
3. Equal to Total Float.
4. Less than Independent Float
A.1 and 4 are correct
B.2 and 3 are correct
C.1 and 4 are correct
D.1 and 2 are correct

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Records And Database Management

Authors: Jeffrey R Stewart Ed D, Judith S Greene, Judith A Hickey

4th Edition

0070614741, 9780070614741

More Books

Students also viewed these Databases questions

Question

6. Effectively perform the managers role in career management.

Answered: 1 week ago