7. Consider the following set of processes, with the arrival time and the length of the CPU burst given in mil- liseconds ISE 218 -
7. Consider the following set of processes, with the arrival time and the length of the CPU burst given in mil- liseconds ISE 218 - Fall 2018 Page 1 of2 Homework#7 ProcessArrival Time Burst Time 0 4 P3 a. [4 pts] Draw a Gantt chart similar to one from the lecture notes that illustrates the execution of the processes using the shortest-job-first CPU scheduling algorithm b. [4 pts] What is the waiting time of each process? c. [2 pts] What is the average waiting time of the processes