7 D Ltd is installing a state - of - the - art air traffic control system for National Aviation Authority. The work started on

7 D Ltd is installing a state-of-the- art air traffic control system for National
Aviation Authority. The work started on 1 July 2022 with an expected
finalisation date of 30 June 2025. The contract value is 4,000,000. The
agreed price is 4,000,000.
Expenses realised to 1,600,000.
Fifty percent job on the contract was completed.
Certificate of work finished have been issued by the engineering
department, to the value of 2,000,000.
Required
What is the contract profit in year 2023 and what have the carrying value
of the contract asset on 30 June 2023.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Personal Finance An Integrated Approach

Authors: Bernard J. Winger

4th Edition

0198520972, 9780132696302

More Books

Students also viewed these Finance questions

Question

4. Identify some patterns of how people consume popular culture.

Answered: 1 week ago