Question
7. Draw a CE diagram showing different factors that could contribute to delaying the project. 8. describe how risks are reduced over the lifespan of
7. Draw a CE diagram showing different factors that could contribute to delaying the project.
8. describe how risks are reduced over the lifespan of a project such as this one
9. with reference to the concerns expressed upon completion of the construction, discussion
statement. "Risks always relate to the future. There is no such thing as a past risk"
Case - Reference
Newtown, South Africa is a suburb of Johannesburg that boasts a rich cultural heritage. As
part of an attempt to help rejuvenate Newtown, the Nelson Mandela Bridge was constructed
to link it to important roads and centers of commerce in Johannesburg. Spanning 42
electrified railway lines the bridge (Figure 10.10) has been acclaimed for its functionality and
beauty.
Lack of space for the support pylons (towers) between the railway lines dictated that the
bridge design would have a long span. This resulted in a structure with the bridge deck
supported by stay cables from pylons of unequal height. The pylons on the northern side are
48 meters high and those in the southern side are 35 meters high.
The pylons are composite columns consisting of steel tubes that dad to be filled with
concrete after being hoisted into the vertical position. The decision was made to pump the
concrete into the tubes through a port at the bottom of each tube. This had to be done in a
single operation. Although the technology for casting concrete this way was not new, the
columns were the highest concrete.
The pump for the concrete was placed at ground level between the electrified railway
lines, which exposed workers to the risks of being near continuous rail operations. The
pumping method posed the risk of the stone aggregate and cement in the concrete mixture
segregating in the pylon tubes before the concrete solidified, witch would compromise the
strength of the concrete.
Another risk was that the pump might fail and result in the concrete solidifying in an
uncompleted pylon. Rendering further pumping of concrete from the bottom impossible. Two
contingencies were considered. An additional pump on standby, and completing the process
by pouring concrete from the top of the pylon.
Figure 10.10
Nelson Mandela Bridge. Johannesburg.
Source: Stock.
CASE 10.3 THE NELSON MANDELA BRIDGE33
PART II PROJECT LIFE CYCLE
The concrete had to be transported by trucks to the site, which risked interrupting the
concrete supply owing to traffic congestion in the city.
Despite working over a busy yard with trains running back and forth, no serious accident
occurred at any time in the 420,000 labor-hours project. The pump never failed and
constriction finished on time, The stay cables-totaling 81,000 meters in length-were installed
and the bridge deck lifted off temporary supports, all while the electrified railway lines
beneath remained alive. Upon completion of the bridge, some feit the the cost incurred to
reduce the risks had been excessive others held that the risks were too high and not enough
had been done to reduce them.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started