Answered step by step
Verified Expert Solution
Question
1 Approved Answer
7. The New York City is comparing two plans for supplying water to a newly developed subdivision: Plan A will take care of requirements for
7. The New York City is comparing two plans for supplying water to a newly developed subdivision: Plan A will take care of requirements for the next 15 years, and at the end of this time, the initial cost of $1,100,000 will have to be duplicated to meet the requirements of subsequent years. The facilities installed at years 0 and 15 may be considered permanent. However, certain supporting equipment will have to be replaced every 30 years from the installation dates at a cost of $80,000. Operating costs are $40,000 a year for the first 15 years and $80.000 thereafter, although they are expected to increase by $1.000 a year beginning in the 21* year. Plan B will supply all requirements for water indefinitely into the future, although it will be operated only at half capacity for the first 15 years. Annual costs over this period will be $40,000 and will increase to $60,000 beginning in the 164 year. The initial cost of Plan B is $1,300,000. The facilities can be considered permanent, although it will be necessary to replace $200,000 worth of equipment every 30 years after the initial installation. The city will charge the subdivision for the use of water on the basis of the equivalent annual cost. At an interest rate of 10%, determine the equivalent anmal cost for each plan, and make a recommendation to the city. 7. The New York City is comparing two plans for supplying water to a newly developed subdivision: Plan A will take care of requirements for the next 15 years, and at the end of this time, the initial cost of $1,100,000 will have to be duplicated to meet the requirements of subsequent years. The facilities installed at years 0 and 15 may be considered permanent. However, certain supporting equipment will have to be replaced every 30 years from the installation dates at a cost of $80,000. Operating costs are $40,000 a year for the first 15 years and $80.000 thereafter, although they are expected to increase by $1.000 a year beginning in the 21* year. Plan B will supply all requirements for water indefinitely into the future, although it will be operated only at half capacity for the first 15 years. Annual costs over this period will be $40,000 and will increase to $60,000 beginning in the 164 year. The initial cost of Plan B is $1,300,000. The facilities can be considered permanent, although it will be necessary to replace $200,000 worth of equipment every 30 years after the initial installation. The city will charge the subdivision for the use of water on the basis of the equivalent annual cost. At an interest rate of 10%, determine the equivalent anmal cost for each plan, and make a recommendation to the city
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started