Question

1 Approved Answer

8 0 % Estimate ( days ) Max. duration ( days ) A 1 7 2 2 D 1 4 1 5 E 7 1

80% Estimate (days) Max. duration (days)
A 1722
D 1415
E 710
F 911
H 1418
For the above data for critical path with the precedence A-D-E-F-H, the recommended project duration for 90% confidence level using USM is? How many days?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Economics Of Money Banking And Financial Markets

Authors: Frederic Mishkin

10th Global Edition

0273765736, 978-0273765738

More Books

Students also viewed these Finance questions

Question

Acceptance of the key role of people in this process of adaptation.

Answered: 1 week ago

Question

preference for well defined job functions;

Answered: 1 week ago