Question
1 Approved Answer
8 children and 12 men complete a certain piece of work in 9 days. If each child takes twice the time taken by a man
8 children and 12 men complete a certain piece of work in 9 days. If each child takes twice the time taken by a man to finish the work, in how many days will 12 men finish the same work ?
a. 8
b. 15
c. 9
d. 12
Step by Step Solution
★★★★★
3.37 Rating (150 Votes )
There are 3 Steps involved in it
Step: 1
The detailed answer for the above que...