9 (2 points) Calculate the cost performance index (CPI) and indicate if the project is over budget or not, if BCWP is $90,000, BCWS is
9 (2 points) Calculate the cost performance index (CPI) and indicate if the project is over budget or not, if BCWP is $90,000, BCWS is $136,778, and ACWP is $112,000? A) 0.803 - Yes, over budget B) 0.658 - Yes, over budget C) 1.875 - No, under budget D) 1.143 - No, under budget